G98 and G99 explained: which one applies to your system

Two forms, one threshold, and you will never fill in either of them yourself. Here is what your installer sends to the network operator, when it goes in, and how long it holds things up.

Updated 4 August 2026 · from the OVO Solar & Battery team

An OVO engineer using a torch to inspect roof timbers in a loft beside a drum of cable

The short answer

G98 and G99 are the two routes for connecting a home generator to the electricity network. G98 covers smaller systems and works on a fit first, tell them after basis. G99 covers larger ones and requires permission before any work starts. One number decides which route you are on: the AC rating of the inverter, measured per phase.

G98 and G99 grid connection routes Two grid connection routes compared, one above the other. Under G98, the installer fits the system first and then notifies your network operator that it is connected. Under G99, the installer applies for permission first and waits for approval before the system goes in. A closing note explains that your network operator owns the local grid and is not your energy supplier, and that which route applies depends on the size of your system. G98 and G99: how they differ G98 Fit first, notify after The installer fits the system, then notifies your network operator that it is connected. or G99 Apply first, fit after approval The installer applies for permission and waits for approval before the system goes in. Your network operator owns the local grid. It is not your energy supplier. Which route applies depends on the size of your system.
The two connection routes, and which one comes first.

3.68kW per phase is the line

At or below 3.68kW per phase, which is 16A per phase, your system goes down the G98 route and gets notified after commissioning. Above it, you are into G99 and the network operator has to approve the design before the scaffold goes up.

Who your DNO is, and why they get a say

Your Distribution Network Operator owns and runs the cables and substations that bring electricity to your street. Great Britain has 14 licensed DNO areas between six groups, and you do not choose yours any more than you choose your postcode. Because a solar system pushes power back into their network, they get a say in what connects to it. Your regional partner deals with the same DNO every week and handles the whole process for you, and you can find yours on the coverage page.

  • Use the Energy Networks Association postcode tool to look it up in seconds.
  • Call 105, the free national number, and ask.
  • Read the first two digits of the bottom line of your MPAN, printed on your electricity bill.

G98: fit first, notify within 28 days

G98 is a notification, not a request. The system is designed, installed and commissioned, and the installer then submits the G98 form to the DNO within 28 days. There is no waiting period built into your project and no approval to chase. This is the route most single phase homes take, which is why a 3.68kW inverter is the standard specification on a typical UK domestic install.

A properly completed G98 cannot be refused

If the system sits inside the threshold and the paperwork is filled in correctly, the DNO has no grounds to reject it. That is the whole point of the connect and notify route, and it is why the vast majority of domestic installations never involve a wait.

G99: apply first, then fit

Above 3.68kW per phase, the order reverses. The installer submits a G99 application and the DNO assesses whether the local network can take the extra generation before anything is fitted. A standard determination usually takes around 4 to 8 weeks. Fast track routes can come back in about 2 weeks, and genuinely complex cases can run to 12. The application itself is free, though installers may charge an admin fee for preparing it, and in rare cases the DNO can require network reinforcement that carries a cost.

G98G99
Applies whenInverter is 3.68kW per phase or less, which is 16A per phaseInverter is above 3.68kW per phase, or above 11.04kW on three phase
Permission firstNo. Fit, commission, then notifyYes. Nothing is installed until the DNO responds
TimingForm submitted within 28 days of commissioningAround 4 to 8 weeks for a standard decision, about 2 on a fast track
Can it be refusedNo, not if it is properly completedYes, and reinforcement work can be required
Who submits itYour installerYour installer

Both thresholds refer to the AC rating of the inverter, per phase, not to the panel capacity on the roof.

Your local OVO expert will tell you on the call which route your system takes and what it adds to the timeline. The 45 minute video design is free and there is no home visit.

Get your free quote

The threshold is the inverter, not the panels

This is the part that surprises people. The 3.68kW figure is the inverter's AC output rating, so it does not cap how many panels go on the roof. Arrays are routinely oversized relative to the inverter, with industry practice putting the ratio somewhere between 1.10 and 1.30, and you can comfortably sit well above 4kWp of panels on a 3.68kW inverter and still be a G98 job. Extra panels are cheaper than a bigger inverter once the scaffold and the crew are paid for, which is the argument in our guide to filling the roof first time and in the cost guide. Where a battery is in the design, the sizing order changes again, and that is covered in the solar and battery strategy.

How solar electricity reaches your home Five steps in order, stacked from top to bottom. One, the panels make DC electricity from daylight. Two, the inverter converts that DC into the AC electricity a home runs on. Three, your home uses whatever it needs at that moment. Four, the battery stores the surplus for later. Five, anything still left over is exported to the grid. How solar reaches your home 1 Panels Daylight on the roof makes DC electricity 2 Inverter Converts the DC into the AC your home runs on 3 Your home Takes what it needs first, before anything else 4 Battery Stores the surplus to use after dark 5 Grid Whatever is still left over is exported
The inverter is the box the 3.68kW threshold is measured at.

Single phase or three phase changes the ceiling

Step 1

Know what is at stake

Most UK homes are single phase and capped at 3.68kW of inverter under G98. A three phase home gets 11.04kW under the same connect and notify rule, which is a very different system before anyone applies for anything.

Step 2

Find the service head

It is the sealed unit where the supply cable enters the property, normally next to or just below the meter.

Step 3

Count the fuses and the wires

Single phase typically shows one cut-out fuse and two wires, a live and a neutral. Three phase shows three 100A fuses and four wires, three lives and a neutral.

Step 4

Check the meter markings

Labels reading L1, L2 and L3 are a reliable sign of a three phase supply.

Step 5

Take a photo for your design call

One clear picture of the meter and service head lets your regional partner confirm the phase and the connection route while you are still on the video call.

If the DNO turns the application down

  1. Pay for the network reinforcement the DNO has specified, if the quoted cost is proportionate to the system.
  2. Cap the inverter at 3.68kW, or apply export limitation, so the design drops back under the G98 threshold.
  3. Decline the connection and redesign the system around a smaller inverter with more panels behind it.
  4. Reapply later, because local network capacity changes as reinforcement work is carried out in the area.

Get a written quote on the call, with the grid application route already worked out for your property. Book a free 45 minute video design with your regional partner.

Get your free quote

OVO SEG Install Exclusive pays 20p per kWh where OVO installs both solar and battery, or 15p per kWh for solar only. The exclusive rates require you to take your electricity supply from OVO and are subject to system size limits. OVO's standard SEG rate of 4p per kWh is open to customers of any supplier. Rates correct at August 2026 and subject to change. Full conditions are in our export rate guide.

FAQs

Grid connection questions, answered

Do I have to fill in a G98 or G99 form myself?

No. On a standard certified installation the installer handles the whole process end to end, from working out which route applies to submitting the paperwork and dealing with the DNO's questions. Your local OVO expert does it as part of the job, and you will not be asked to sign a network application yourself.

How long does a G99 application take?

A standard determination usually takes around 4 to 8 weeks from submission. Fast track routes can come back in roughly 2 weeks, and complex cases where the local network is already constrained can stretch to about 12 weeks. Nothing is installed until the answer arrives, so it is worth having the design call early if you suspect you are over the threshold.

Can I fit more than 4kW of panels and stay on G98?

Yes. The threshold applies to the inverter's AC rating, not to the panel capacity on the roof. Oversizing an array relative to the inverter is normal practice, with typical ratios between 1.10 and 1.30, so a 3.68kW inverter can sit behind meaningfully more than 4kWp of panels and remain a connect and notify job.

Does the application cost anything?

The application itself is free. Some installers charge an admin fee for preparing and submitting it, and in the rare cases where the DNO requires network reinforcement before it will accept the connection, that work carries a cost which is quoted separately.

How do I find out who my DNO is?

Great Britain has 14 licensed DNO areas owned by six groups, and yours is set by where you live. You can use the Energy Networks Association postcode tool, call 105 free of charge, or read the first two digits of the bottom line of the MPAN on your electricity bill.

Can a G98 notification be rejected?

Not if it is properly completed and the system genuinely sits within the 3.68kW per phase limit. G98 is a notification rather than a request, which is the reason most domestic installations go ahead without any waiting on the network operator.

What is the maximum I can install without prior approval?

3.68kW of inverter on a single phase supply, or 11.04kW on three phase. Above those figures you need a G99 approval before installation. Whether your home is single or three phase therefore has a much bigger effect on system size than most people expect.

Figures and specifications in this guide are sourced below and were checked on the date shown. Rates and product specifications change; we confirm the current picture on your free design call.

Sources
  • G98 connect and notify process, the 28 day notification window, and that a completed notification cannot be rejected sunsave.energy
  • G99 approval requirement, 4 to 8 week standard determination, fast track and complex case timescales, free application and refusal options sunsave.energy
  • Threshold applies to inverter AC rating rather than panel capacity, and the 3.68kW single phase and 11.04kW three phase limits sunsave.energy, spiritenergy.co.uk
  • What a DNO is, the 14 licensed areas across six groups, the 105 number and the MPAN lookup ovoenergy.com, uw.co.uk
  • Identifying a single phase or three phase supply from the service head, fuses and meter markings ukpowernetworks.co.uk
  • Inverter loading ratios of 1.10 to 1.30 and the case for oversizing an array relative to the inverter aurorasolar.com, freedomforever.com
  • OVO SEG rates and eligibility conditions ovoenergy.com
Free, no obligation

Get your free quote

Two minutes. We confirm your video slot within one working day.

We can only install for homeowners, as the system is fixed to the property. Do carry on if you own it, or you are about to.
We are not able to install on flats and apartments because the roof is shared. Send your details anyway and we will let you know if that changes.
1 Where is your home?
Please add your full postcode
Please add your house number
Please add your street
2 About you
Please add your first name
Please add your last name
Please add a UK number
Please add a valid email
3 Your property
Do you own your home?
Please let us know
Property type
Please choose your property type
4 What you are after
Please pick a range
Please choose an option
Please choose an option
5 When shall we call?
Best time for you (optional, but it helps)
We never call after 8pm.
Free, no obligation No home visit needed Your quote on the call